Westbound Fix50 work has - in fact - started

05/02/2014 4:56 PM

05/02/2014 4:58 PM

Q: Hi there! With the Fix 50 project ahead of schedule, will phase one of the westbound construction start earlier than May 27 as planned? Thanks for your help and for keeping us posted on all the construction news. - Adeline Yee, El Dorado Hills

A: No, it won’t. It looks likely that the contractor will finish repaving the eastbound side of the freeway before his May 21 deadline. That means crews will then move to the westbound side, and start 24-hour closures there. But the contractor has agreed not to start the westbound closures prior to May 27. One reason is that the state does not want any lanes at all closed during the Memorial Day weekend.

That said, crews already are doing temporary night-time closures of up to two lanes on the westbound side for prep work. That work is being done most nights, between 10 p.m. and 5 a.m. Workers and equipment are cleared out and all lanes open for each morning commute.

Submit your question to The Sacramento Bee’s Fix50 answer team

Read all the Fix 50 Q&A’s

Editor's Choice Videos

 

Join the Discussion

The Sacramento Bee is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere on the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Terms of Service